On August 12, China Communications Construction Company Limited's CCCC Third Highway Engineering Co., Ltd. won the bid for the construction of Phase II section between Wencheng and Rui'an of Zheqiang Long Li Wen Expressway. The subsidiary proposed completion of the works in 36 months and for RMB 630 million.

The project will cover the section between Wencheng county, Wenzhou City and Rui'an City. With investment totaling RMB 5 billion, the Zheqiang Long Li Wen Expressway consists of six sections and measures 40.32 kilometers in length. The section for which CCCC Third Highway Engineering Co., Ltd. has won the bid is located in Xuekou Town, Wencheng County and is 5.44 kilometers in length. The project will cover the construction of a main roadbed, a bridge (around 844 meters), two long tunnels (total length 4,524 meters), a main road, a Mayu interconnection cable, and temporary connection lines for Wencheng hub.